I have a list of things that need to be done for each hole at The Grove. You might want to sit down as it is a long list.
Materials available- Mulch- There is a big pile on hole 2 fairway, a pile on 9 fairway and a small pile on 17 fairway. Gravel- There is a pile or 3/4 gravel and a pile of 3/8 gravel on the walkout from 1 to 2. There is a pile of 3" gravel on 16 fairway. It is tough to shovel but lasts forever. There is some 3/4 gravel on the way from the city.
Hole 1- Needs mulch near bench and any other muddy areas (looks like some of that has already been done). needs another nice bench. a little bit of 3/4 gravel around the teepad. Regular trash can emptying and trash pick up (on all holes). Wooden stakes hammered in on the OB road line behind the basket(or a painted line so it will be easy to mow and still know where OB is)
Hole 2- #/4 gravel around teepad, 1 more bench
Hole 3- Gravel and rubble to build up around teepad, pour teepad extension, mulch around basket, maybe a bench or two if we can figure out where they could go.
Hole 4- Wooden stakes to show OB line between swamp area and non- swamp area, #/4 gravel around teepad, Scott Wales will eventually build benches
Hole 5- mulch around basket 5B position, pour teepad extension, maybe another bench to go with the picnic table
Hole 6- clean up loose wood debris on fairway, pour teepad extension, 2 benches
Hole 7- pour teepad extension and add on to the left side of teepad for new route that opened up on left.
Hole 8- 3/4 gravel around teepad, benches
Hole 9- 2 benches, move stumps by teepad
Hole 10- 3/4 gravel around teepad, benches, mulch on green
Hole 11- mulch around teepad (done), back fill behind teepad
Hole 12- mulch on 12a and 12b greens, build up rubble gravel to make larger teepad area, benches
Hole 14- 3/4 gravel around teepad, pour teepad extension, mulch on path from 14 to 15, benches
Hole 15, 3/4 gravel around teepad, benches
Hole 16- 3/4 gravel around teepad, benches
Hole 18- Have Tom Chrestman locate teepad with spray paint, dig out for teepad, add 2-3" 2/4 gravel, tamp with Tom Chrestmans vibrating tamper, build form for large teepad-minimum 12' length x 5' width finish concrete with extra grippy "rake-broom-rake" finish.
I met Brad out working on hole 5 today. He was spreading bark there and around hole 6 teepad. next he was going to do some weed-eating....Thanks Brad.